1. Deciding on installation strategy

Familiarise yourself with the results of the wind load calculation and decide on the
procedure for the installation.
Consider how best to deploy personnel, materials and equipment. In this way you
will achieve a fast, correct and efficient installation.

2. Preparing the roof for fastening

Prepare the roof for laying out the waterproof membrane (e.g. prepare substrate,
vapour barrier, thermal insulation, fleece etc.).
It is important to observe local regulations and manufacturers' instructions.
Recommendation: Prepare only a roof area which can be fixed and covered
by the end of each day.
Before rolling out the waterproof membrane, steps 3 and 4 have to be carried out.

3. Measuring and marking fastening points

Measure the locations of the fastening points in accordance with the wind load
calculation and mark these on the prepared roof surface using e.g. a chalk line.